Linkedin-in X-twitter Instagram
  • Home
  • News Room
    • Projects
  • Offsite Magazine
    • Latest Issue
    • Back Issues
    • Supplements
    • Advertise
    • Print Subscription
    • Digital Sign Up
  • Events
    • Explore Offsite Conference
    • Offsite Awards
    • Factory Tours
    • Roundtables
  • Offsite Info
    • About Offsite Hub
    • Offsite Technologies
    • Supplier Directory
    • Glossary of Terms
  • Home
  • News Room
    • Projects
  • Offsite Magazine
    • Latest Issue
    • Back Issues
    • Supplements
    • Advertise
    • Print Subscription
    • Digital Sign Up
  • Events
    • Explore Offsite Conference
    • Offsite Awards
    • Factory Tours
    • Roundtables
  • Offsite Info
    • About Offsite Hub
    • Offsite Technologies
    • Supplier Directory
    • Glossary of Terms

PROJECTS

PBBS – HLM Architects & Laing O’Rourke

SECTOR

Commercial

CONTRACTOR

HLM Architects & Laing O'Rourke

TECHNOLOGY

Components

Project Overview

The Demonstrator was part of PBBS, a £3m R&D project supported by Innovate UK and led by Laing O’Rourke. Underpinned by the intention to ‘standardise the invisible and customise the visible’, the team aimed to standardise the interfaces while allowing architectural expression to meet client requirements. The Platform Design for Manufacture and Assembly (P-DfMA) comprises a kit of parts made from standardized components.

The system innovates the design process by allowing for the iterative use of limited components that have been optimised for multiple sector building design. Each component has its own product innovations, incorporating design configuration choices, to form a platform capable of designing projects with variations in both internal layout and external façade design. The Demonstrator, containing a typical classroom and 1 bedroom flat joined by service distribution corridors, was the prototype building which brought together the components in real life. Certainty, Productivity, Sustainability underpinned the development of a high-performing platform to customize the visible and standardize the invisible to achieve beyond the current Laing O’Rourke delivery methods.

The Demonstrator has provided significant savings from the use of the platform design:

– Up to 50% Reduction in technical & fabrication design

– 40% reduction in manufacturing lead time

– 25% reduction in manufacturing labour

– 50% Reduction in Assembly time & 70% reduction labour vs traditional construction

– Up to 50% reduction in embodied carbon

– Up to 30% reduction in operational carbon

Plus:

– Industry leading air-tightness performance

– 30% overall faster delivery The platform demonstrated labour savings through simplified products and a multi-skilled assembly team.

It has transformed the way they build and opens the potential for diversity in the skills and training. The result is a completely different way of working, where reductions in labour benefit the industry. To aid industry adoption, Laing O’Rourke incorporated four guides to ensure that the quality designed into the system would translate into  improvements in efficiency, speed, safety, performance, and carbon savings; HLM delivered the Design Guide for structural, architectural and MEP design.

The system supplies all services including MEP and is applicable to multiple sectors. The demonstrator proved educational and residential application; healthcare and mixed use/commercial sectors will also be targeted. All of this allows the Demonstrator platform design to meet the goals of increased construction productivity and reduced carbon targets while still giving architects the ability to create thoughtful designs for our clients.

SHARE

PROJECTS YOU MIGHT BE INTERESTED IN…

Intrastack Ennerdale Avenue

October 7, 2024

British Offsite Abbey Quay, Barking, Weston Homes

October 7, 2024

Langley Square, Mill Pond, Dartford

September 11, 2024

LATEST NEWS

Involving the workforce is key to making offsite construction work, says Laing O’Rourke’s James Turner

November 9, 2026

Frameclad Launch Approved Installer Network

November 4, 2026

Repeatable platforms are helping improve project delivery, says Kier Group’s Andrew Dewdney

November 4, 2026

MMC Ireland National Conference Returns for 2027 with Inaugural Awards Ceremony

November 4, 2026

LSFA Introduces New Integrator Membership Category

November 3, 2026

CLICK HERE TO READ THE LATEST ISSUE

  • NEWS ROOM
  • SUPPLIER DIRECTORY
  • EVENTS
  • OFFSITE INFORMATION
  • ABOUT US
  • PRIVACY
  • HUB OPPORTUNITIES
  • OFFSITE MAGAZINE
  • BACK ISSUES
  • SUPPLEMENTS
  • ADVERTISE
  • SUBSCRIPTION

SIGN UP FOR OUR

LATEST NEWSLETTER

SUBSCRIBE TO OUR

OFFSITE MAGAZINE

Get in touch

  • T: 01743 290001
  • E: [email protected]

© OFFSITE HUB 2026 - All Rights Reserved