Linkedin-in X-twitter Instagram
  • Home
  • News Room
    • Projects
  • Offsite Magazine
    • Latest Issue
    • Back Issues
    • Supplements
    • Advertise
    • Print Subscription
    • Digital Sign Up
  • Events
    • Explore Offsite Conference
    • Offsite Awards
    • Factory Tours
    • Roundtables
  • Offsite Info
    • About Offsite Hub
    • Offsite Technologies
    • Supplier Directory
    • Glossary of Terms
  • Home
  • News Room
    • Projects
  • Offsite Magazine
    • Latest Issue
    • Back Issues
    • Supplements
    • Advertise
    • Print Subscription
    • Digital Sign Up
  • Events
    • Explore Offsite Conference
    • Offsite Awards
    • Factory Tours
    • Roundtables
  • Offsite Info
    • About Offsite Hub
    • Offsite Technologies
    • Supplier Directory
    • Glossary of Terms

PROJECTS

NHS Nightingale Hospital Exeter – Stride Treglown

SECTOR

Health

CONTRACTOR

Stride Treglown

TECHNOLOGY

Volumetric modular

LOCATION

Exeter

nightingalehospitalexeter_2022_lowres_6
Nightingale Hospital Exeter
Nightingale Hospital Exeter2
Nightingale Hospital Exeter3
Nightingale Hospital Exeter4

Project Overview

A complex brief In terms of scope, scale and complexity, NHS Nightingale Hospital Exeter differed to the other pandemic field hospitals. The ambition was to deliver  something more than a temporary facility. Royal Devon and Exeter NHS Foundation Trust required a fully functional, permanent clinical facility. Added to this, large sites with good existing infrastructure (conference venues) were not available across the South West.

So a redundant retail shed was selected as the preferred option. Our unique solution: the speed of construction, site restrictions and availability of materials required innovative procurement of modular assemblies and off-site components. All new infrastructure was brought to the site and the shed was more than doubled in footprint through 60 MMC volumetric units. As the last of the eight UK Nightingale Hospitals to be built, we applied lessons learned from the emerging COVID-19 response to deliver an innovative and flexible facility.

Our model consisted of five wards each with 24 beds. The segregated wards enable the hospital to care for the greatest range of patients – from the sickest through to those recovering or with less severe problems. Diagnostic imaging, to allow for cancer screening, was also included in the scheme to provide greater flexibility. Flexibility in use NHS Nightingale Hospital Exeter was put into operation in June 2020, initially taking non-COVID patients to relieve the pressure on regional hospitals. It received its first COVID-19 patients in November 2020. Our innovative ward design meant that this facility was one of only two in the country to continually receive COVID-19 patients.

After a reduction in cases, the hospital was used for cancer screening. Phase Two – Recovering Post- Covid Waiting Lists In 2021, the team was approached to transform the facility into a full planned care centre to help clear the backlog of clinical demand created by the pandemic. The objective was to make best use of the existing space created for the Nightingale Hospital for elective recovery by creating:

-Orthopaedic short stay theatres

-Diagnostic hub with CT/MRI capacity (one of the first in Devon)

-Rheumatology unit

-Ophthalmology facilities

The unique existing hospital design enabled the team to adapt the main bed spaces (60 volumetric units) into the various clinics and treatment rooms required for the new community hub. To provide the facilities for Orthopaedic Surgery in a short time-frame, the design team radically sought to procure the high-tech spaces using offsite  manufacture. Two Operating Theatres, a recovery space was transported to site and craned onto a prefabricated steel support deck in the car park and linked to the main building.

SHARE

PROJECTS YOU MIGHT BE INTERESTED IN…

Intrastack Ennerdale Avenue

October 7, 2024

British Offsite Abbey Quay, Barking, Weston Homes

October 7, 2024

Langley Square, Mill Pond, Dartford

September 11, 2024

LATEST NEWS

Involving the workforce is key to making offsite construction work, says Laing O’Rourke’s James Turner

November 9, 2026

Frameclad Launch Approved Installer Network

November 4, 2026

Repeatable platforms are helping improve project delivery, says Kier Group’s Andrew Dewdney

November 4, 2026

MMC Ireland National Conference Returns for 2027 with Inaugural Awards Ceremony

November 4, 2026

LSFA Introduces New Integrator Membership Category

November 3, 2026

CLICK HERE TO READ THE LATEST ISSUE

  • NEWS ROOM
  • SUPPLIER DIRECTORY
  • EVENTS
  • OFFSITE INFORMATION
  • ABOUT US
  • PRIVACY
  • HUB OPPORTUNITIES
  • OFFSITE MAGAZINE
  • BACK ISSUES
  • SUPPLEMENTS
  • ADVERTISE
  • SUBSCRIPTION

SIGN UP FOR OUR

LATEST NEWSLETTER

SUBSCRIBE TO OUR

OFFSITE MAGAZINE

Get in touch

  • T: 01743 290001
  • E: [email protected]

© OFFSITE HUB 2026 - All Rights Reserved