Linkedin-in X-twitter Instagram
  • Home
  • News Room
    • Projects
  • Offsite Magazine
    • Latest Issue
    • Back Issues
    • Supplements
    • Advertise
    • Print Subscription
    • Digital Sign Up
  • Events
    • Explore Offsite Conference
    • Offsite Awards
    • Factory Tours
    • Roundtables
  • Offsite Info
    • About Offsite Hub
    • Offsite Technologies
    • Supplier Directory
    • Glossary of Terms
  • Home
  • News Room
    • Projects
  • Offsite Magazine
    • Latest Issue
    • Back Issues
    • Supplements
    • Advertise
    • Print Subscription
    • Digital Sign Up
  • Events
    • Explore Offsite Conference
    • Offsite Awards
    • Factory Tours
    • Roundtables
  • Offsite Info
    • About Offsite Hub
    • Offsite Technologies
    • Supplier Directory
    • Glossary of Terms

PROJECTS

Assembly Building C – PCE

SECTOR

Commercial

CONTRACTOR

PCE Ltd

TECHNOLOGY

Hybrid technology

20220608_094414
pce ltd
pce ltd2
pce ltd3
pce ltd4

Project Overview:

PCE Ltd has designed, manufactured and constructed a 14 storey HybriDfMA office building using offsite manufactured structural steel and precast concrete components together with in-situ reinforced concrete, forming the PCE Hybrid Frame System. The HybriDfMA framed building provides 92,000 sq. ft. of office space utilising PCE’s  experience of Modern Methods of Construction (MMC), Offsite engineering and providing as much Offsite construction as possible in a very busy city centre location.

Assembly Building C is a prestige HybriDfMA framed office building. The Hybrid design mentality has enabled PCE to think ‘outside of the box’ to incorporate new ideas providing a ‘Kit of Parts’, that enables the creation of visually appealing structures like Building C, and the ability to merge precast concrete and steel into a design that provides a building that can be built faster, safer, and more efficiently and is evident in the attention to detail through the design process.

Modern Methods of Construction (MMC) are captured in their infancy through the design stage to ensure that as much offsite precast concrete manufacturing can be incorporated and ready for manufacturing and delivery. The project pulled together exposed architectural precast concrete sandwich panels that are part of the main core to the north of the building with precast concrete elements including precast concrete twin and solid walls where attention is being paid to the requirement that the building is to have exposed, unpainted finished concrete.

The design of the architectural panels was very high on the city planners’ radar, where attention to detail in design was required to ensure a stunning, visual building, complementary to the Bristol skyline. A total of 44 architectural sandwich panels, and over 400 precast concrete twin and solid walls were manufactured at various factories throughout the UK along with over 1000 hollowcore units. The high specification was achieved with collaboration and communication with the suppliers to ensure the  project had minimal finishing works on site.

A large investment was made by PCE in the design stage to ensure the structure was erected with a just in time philosophy with precast lifted off in sequence straight from the lorry directly into position. In addition to the structure we are also providing a modular riser wall system to enclose theoretical risers. This innovative solution provides a fire rated enclosure which is constructed progressively with the frame construction from a modular panel system.

SHARE

PROJECTS YOU MIGHT BE INTERESTED IN…

Intrastack Ennerdale Avenue

October 7, 2024

British Offsite Abbey Quay, Barking, Weston Homes

October 7, 2024

Langley Square, Mill Pond, Dartford

September 11, 2024

LATEST NEWS

Involving the workforce is key to making offsite construction work, says Laing O’Rourke’s James Turner

November 9, 2026

Frameclad Launch Approved Installer Network

November 4, 2026

Repeatable platforms are helping improve project delivery, says Kier Group’s Andrew Dewdney

November 4, 2026

MMC Ireland National Conference Returns for 2027 with Inaugural Awards Ceremony

November 4, 2026

LSFA Introduces New Integrator Membership Category

November 3, 2026

CLICK HERE TO READ THE LATEST ISSUE

  • NEWS ROOM
  • SUPPLIER DIRECTORY
  • EVENTS
  • OFFSITE INFORMATION
  • ABOUT US
  • PRIVACY
  • HUB OPPORTUNITIES
  • OFFSITE MAGAZINE
  • BACK ISSUES
  • SUPPLEMENTS
  • ADVERTISE
  • SUBSCRIPTION

SIGN UP FOR OUR

LATEST NEWSLETTER

SUBSCRIBE TO OUR

OFFSITE MAGAZINE

Get in touch

  • T: 01743 290001
  • E: [email protected]

© OFFSITE HUB 2026 - All Rights Reserved